Project Description
Client: McLaughlin & Harvey
Location: Luton
Works undertaken: Re-modelling of existing Pier A on airside and the construction of a new Pier B. This project involved deep drainage, mass concrete footings, casting in holding down bolts for structural steel, casting of elephants feet to structural steel, forming new concrete slab and reinstating of existing hard standings.